- Previously given Paper 09ATC-0232 delivered at the SAE Aerotech conference in Seattle in 2009 reports on the E6000 machine installing slug rivets with the EMR. Paper 2015-01-2491given at the SAE conference in Seattle in 2015 reports on index head rivets being installed with screw driven squeeze process. This paper reports on the screw driven squeeze process installing unheaded slug rivet which is a more complex process. We also report on improvements to the fixture automation.
- Pages
- 4
- Citation
- Zieve, P., "Gantry Horizontal Slug Riveting System," SAE Technical Paper 2024-01-1924, 2024, https://doi.org/10.4271/2024-01-1924.