MPLM Active Mission Preparation: TCS Unique Testing for Risk Mitigation Part 1: Test Description

2004-01-2431

07/19/2004

Event
International Conference On Environmental Systems
Authors Abstract
Content
The Active MPLM system verification spans multiple programs and multiple organizations with multiple interfaces (Shuttle, ISS, MPLM, MELFI); the MPLM CIWG (Cooling Integration Working Group) was formed to provide a forum for working Active MPLM integration issues such as reviewing the interface verifications currently in plan, identifying the remaining risks to first time use of the end-to-end system, and identifying and working to resolve integrated issues with the system.
The purpose of the Unique TCS Testing is to assess the system capability to calibrate the MPLM/Orbiter cooling loop to minimize the risk of inaccurate MPLM flow rate control to the Minus Eighty–degree Laboratory Freezer for the ISS (MELFI), to perform flow characterization testing for all racks location to minimize risk of R/F rack underflow, and to assess loop flow rate control under reduced flow condition to verify system stability.
This paper intends to describe the rational for performing the TCS Unique Testing, the test cases selection, the test configuration and to assess the constraints associated with the first Active MPLM flight.
Meta TagsDetails
DOI
https://doi.org/10.4271/2004-01-2431
Pages
10
Citation
Michele, T., and Keith, P., "MPLM Active Mission Preparation: TCS Unique Testing for Risk Mitigation Part 1: Test Description," SAE Technical Paper 2004-01-2431, 2004, https://doi.org/10.4271/2004-01-2431.
Additional Details
Publisher
Published
Jul 19, 2004
Product Code
2004-01-2431
Content Type
Technical Paper
Language
English